Once the contract is signed, money moves every month. We check each claim and each variation so you pay a fair price and no more.

When you need it

The right moment.

  • When a builder's progress claim arrives and needs certifying.
  • When a variation lands and you need to know if it is fair before you agree.
  • When a latent condition claim appears after excavation starts.
  • When you need a forecast final cost for the board each month.
What you get

The deliverable.

  • Progress claim assessments with a recommended amount and reasons.
  • Variation assessments on entitlement, quantity and rate, measured against the contract.
  • Latent condition assessments with the facts and the cost separated.
  • Monthly cost reports with committed cost, risks and forecast final cost.
  • The final account, agreed and closed.
Why Trugo

Priced by people who have built.

A contractor knows how a variation is built up, because a contractor writes them. We wrote them for more than thirty years. We know which items are real, which are padded and which belong in the original price.

Each assessment is independent. You know what is fair before you agree, not after.

Related work

From the file.

Wellways Services Hub
Community · Tender advice & client QS

Wellways Services Hub

Value
$5.5M
Client
Wellways (not-for-profit)
Service
Tender advice & client QS

Pre-tender cost plan, then financial lead on the Tender Advisory Panel: eight tenders screened, clarified, financially checked and taken through best-and-final offers and value management. Now client QS through construction.

The three leading tenders came in within 5% of our cost plan. The preferred tender was 2.2% above it. The Board approved the recommendation.

Base 48A, Aliro
Industrial · Variation assessment

Base 48A, Aliro

Value
$16.5M
Client
Aliro (developer)
Service
Variation assessment

Independent assessment of a latent condition claim for buried structures, including a first-principles measure of the engineer's footing sketch.

The claim was fair, so we certified it in full. The builder's lump sum was within 2.7% of our own measure. Independence means saying yes when the number is right.

Shrine of Remembrance Drainage & Pathways
Heritage & civic · Post-contract QS

Shrine of Remembrance Drainage & Pathways

Value
$450k
Client
City of Melbourne
Service
Post-contract QS

Progress claim valuations and variation assessments through construction of drainage and pathway works at the Shrine, with advice on a delay claim.

Twenty-eight variations assessed, agreed with the contractor and signed off by Council. The delay claim was tested against the record and did not stand: the contractor had chosen to start two weeks after the site was available.

Questions

Asked often.

How quickly can you assess a variation?

Our standard is a compliance check on a progress claim within two business days and a variation recommendation within five. Urgent items are turned around faster.

Do you attend site?

Yes, when the claim needs it. Some things cannot be measured from a drawing.

Can you step in partway through a project?

Yes. We start with the contract, the claims to date and the open variations, and bring the cost report up to date.

Do you act for builders on variations?

We act for owners and their consultants on post-contract work. We will not act for both sides on the same project.

Start the conversation

Every project starts with honest numbers.

No obligation and no sales process. A direct conversation about what your project needs and what it will cost.