Wellways Services Hub
Community · Tender advice & client QS

Wellways Services Hub

Value
$5.5M
Client
Wellways (not-for-profit)
Service
Tender advice & client QS

Pre-tender cost plan, then financial lead on the Tender Advisory Panel: eight tenders screened, clarified, financially checked and taken through best-and-final offers and value management. Now client QS through construction.

The three leading tenders came in within 5% of our cost plan. The preferred tender was 2.2% above it. The Board approved the recommendation.

Capel Street, North Melbourne
Residential · Feasibility cost plan

Capel Street, North Melbourne

Value
$52M
Client
HLA (developer)
Service
Feasibility cost plan

Feasibility-stage cost plan for a $52M apartment development, priced from the contractor's side: trade by trade, with margin, preliminaries and risk shown separately so the developer could see where the price was built up.

A construction cost the developer could take into the feasibility with confidence, and a clear view of which elements drove it.

Ivanhoe Aquatic Centre pool hall
Aquatic & leisure · Procurement advice

Ivanhoe Aquatic Centre

Location
Ivanhoe
Client
Banyule City Council
Service
Staging & procurement advice

Staging advice to Council on the centre's redevelopment, testing a single-stage build against early gym handover and a live site that keeps the existing gym trading.

Each option set out on programme, staging premium, tender market and contract form, with Council's revenue case tested against the cost of keeping part of the centre open. Council could set direction before design fixed the answer.

Base 48A, Aliro
Industrial · Variation assessment

Base 48A, Aliro

Value
$16.5M
Client
Aliro (developer)
Service
Variation assessment

Independent assessment of a latent condition claim for buried structures, including a first-principles measure of the engineer's footing sketch.

The claim was fair, so we certified it in full. The builder's lump sum was within 2.7% of our own measure. Independence means saying yes when the number is right.

Peerless Foods Tank Farm
Technical · Cost planning

Peerless Foods Tank Farm

Value
$4.5M
Client
Peerless Holdings
Service
Cost planning

Concept design cost plan for a tank farm and pipe bridge at a food manufacturing site: base scope, a separable pavement option, and contingency split into design, site and latent-condition risk.

A priced cost plan, with its risks named, to support the investment decision.

Islamic Museum of Australia, Museum and Cultural Centre
Cultural · ECI cost plan

Islamic Museum of Australia

Location
Thornbury
Client
Key Integrated (ECI)
Service
ECI cost plan

Early contractor involvement cost plan for the new Museum and Cultural Centre, prepared for Key Integrated to inform the Museum's budget before design is complete.

A trade-by-trade budget built ahead of the design, with value management options set out beside it and the site's risks, including a high water table under the basement, priced from the start. The Museum could set its budget with the builder already at the table.

Gosford Student Accommodation, University of Newcastle
Education · Shared BQ

Gosford Student Accommodation

Location
University of Newcastle, Gosford NSW
Client
Tendering builders
Service
Shared BQ

A shared bill of quantities for the tendering builders on the Early Works and Main Works packages, adapting an existing office building into student accommodation under a design and construct contract.

Adaptive reuse under design and construct is where scope hides: in the existing structure, the services and the gaps between design stages. We quantified it trade by trade from documents still in development and kept it current through seven addenda, so every tenderer priced the same, fully described scope.

The Raleigh, Windsor
Residential · Green Star measurement

The Raleigh, Windsor

Location
Windsor
Client
Maxcon Constructions, for the Green Star submission
Service
Green Star measurement

Third-party quantity measure for the Green Star upfront carbon assessment: structure, services, architectural elements, finishes and fit-out, measured as built and entered into the Green Star carbon template.

Measure complete. The same brief is now under way on 68 Green Street, a commercial office in Cremorne. The carbon calculation is only as good as the measure behind it.

Workshop Rebuild, Frankston
Insurance · Insurance reinstatement

Workshop Rebuild, Frankston

Value
$1.2M
Client
Insurance claim
Service
Insurance reinstatement

Quantification of the cost to rebuild a damaged workshop, prepared for the insurer and loss adjuster.

A reinstatement figure built from first principles that the parties could test line by line.

Base repair to full replacement3 options
Sport · Options cost plan

Cyril Cummins Reserve Hockey Pitch, Bellfield

Value
$0.1M–$1.7M
Client
Banyule City Council
Service
Options cost plan

The pitch had subsided around one goal, and the turf was too old to lift and relay. We priced three fixes: a base repair at the goal, a half-pitch replacement and a full replacement.

We also flagged the catch. With subsidence already present, a contractor would likely rebuild the subbase before giving a warranty, which pushes the cheap option toward the dear one.

Regent Caravan Warehouse, Somerton
Industrial · Cost plan & benchmark

Regent Caravan Warehouse, Somerton

Value
$45M
Client
Luna Group
Service
Cost plan & benchmark

A 41,000 m² warehouse with offices on the Austrak estate. We set the cost plan, then tested it against a recently contracted warehouse a third its size.

On paper ours was 16% cheaper per m². With scope aligned, the two sat at parity. A project three times the size should show a scale saving, and the missing saving pointed to preliminaries and margin.

Holbrook Reserve Pavilion, Brunswick West
Community · Preliminary cost plans

Holbrook Reserve Pavilion, Brunswick West

Value
$2.0M
Client
Cassisi Architect for Merri-bek City Council
Service
Preliminary cost plans

A new two-storey sports pavilion of about 270 m²: social room, kitchen, change rooms, umpires’ room and amenities. We priced the schematic design twice in 2024, then followed it into the 2025 redesign.

Construction at $1.52M, total project cost at $1.97M, with contingency, fees, permits and escalation carried. The architect could design to a budget instead of meeting one at tender.

Rosanna Library, east elevation
Community · Split cost assessment

Rosanna Library, Rosanna

Value
$30M
Client
Banyule City Council
Service
Split cost assessment

A $30M development pairing a new 1,300 m² library over two levels with a supermarket and car park. Council needed to know how much of the preferred tenderer’s price belonged to the library.

We built our own detailed cost plan from the tender drawings and tested the tenderer’s breakdown against it. Council knew what the library was worth within the overall scheme.

Tender priced, contract wonWon
Residential · Tender estimate

80 Gozzard Street, ACT

Outcome
Won
Client
Key Integrated
Service
Tender estimate

Fire separation rectification to an existing apartment building: wall-head fire stopping to ten walls, accessed through stair hatches and roof openings, over an eight-week programme.

We priced the tender for Key Integrated, who won it. The client’s clarifications formed part of the contract; we worked through them with the builder and the price held.

Project list

Selected projects.

No.ProjectSectorValueRole
001Gower Street Townhouse DevelopmentResidential$4.5MQS
002Thompsons East P-6 (VSBA)Education$85MEstimator
003Kingsville Child Care DevelopmentCommunity$6MQS
00468 Green Street, CremorneCommercial office-Green Star QS
005Brenbeal Children's CentreCommunity$0.2MQS
006BYD Showroom, BrooklynRetail$2.5MEstimator
007Olympic Leisure Centre RepurposingCommunity$1.4MQS
008The Boulevard, EaglemontCivil$3.2MQS
009Bunnings, MoorabbinRetail$49MCost Planner
010The Base, CraigieburnRetail$44MCost Planner
011Alexandra Avenue Townhouses, South YarraResidential$8.9MQS
012Private Hospital, ChadstoneHealth$55MCost Planner
Quick turnaround and good analysis and advice resulting in us finding real savings. Should have used them earlier in the process.
Matthew TreziseGeneral Manager Projects & Engineering, ABBE
If you ever need quantity surveying services I can't recommend Steve highly enough. He has provided exemplary service for me for the last few years.
Joe KellySenior Project Manager, Banyule City Council
Steve gave our Board the kind of clear, honest cost advice that made a real difference at tender stage.
Theo KrambiasProject Director, Wellways
TRUGO's contractor background saved us money. They knew what the work should genuinely cost, and showed us where the numbers didn't stack up.
Zoran PavlovicManaging Director, HLA
Start the conversation

Every project starts with honest numbers.

No obligation and no sales process. A direct conversation about what your project needs and what it will cost.

Call SteveEnquire